The Financial Participation Agreement between Horry County and the South Carolina Department of Transportation, approved by Horry County Council November 28, 2018, appears to have many flaws not discussed before a resolution was passed allowing Horry County Administrator Chris Eldridge to sign the agreement.
Generally the agreement provides that Horry County will provide up to $25 million per year from Hospitality Fee revenues to fund the construction of I-73 within Horry County (the Project) and SCDOT will oversee the project from design through construction.
The written agreement states, “SCDOT shall provide an Annual Work Plan to the county on the activities proposed by March 31 that the county shall approve prior to June 30 before commencing work in the succeeding fiscal year.”
I find the use of the word “shall” interesting here in that it means a strong assertion or intention of something happening. Are we to take it to mean the county intends to approve the work plan prior to each June 30th? Does this mean county council really has much of a choice in the decision?
At least a half dozen times during the over one hour discussion about the project and the agreement county council members were told by then council chairman Mark Lazarus and/or county staff members, predominantly administrator Chris Eldridge and attorney Arrigo Carotti, that no money could be spent on the project without prior approval from county council.
To support those statements, Carotti quoted to council the first sentence of Section III (D) of the agreement which reads, “SCDOT shall not enter into a construction contract without the County’s prior approval based on considerations that the contract provide a meaningful connection to the proposed I-73 corridor in part or in its entirety.”
What Carotti did not quote were the next two sentences of Section III (D) which read, “The County’s prior approval shall not be required to enter into contract agreements for improvements to SC-22, provided the cost thereof does not exceed the estimates provided in the Annual Work Plan. Nor shall the County’s prior approval be required for any right-of-way acquisition agreement or consultant agreement for work of the Project provided the cost thereof does not exceed the estimates provided in the Annual Work Plan.”
Speak Up…