Horry County Schools Building Projects

The Horry County Schools Selection Committee will meet tomorrow to decide on what firm or firms it will recommend for each of five new school projects.

Three teams, Thompson Turner Construction, First Floor Energy Positive and M.B. Kahn Construction Company, were invited to make offers on at least two projects to all five of the projects, at their discretion.

After several months of review and consideration of the proposals submitted, the committee will recommend one offering team proposal for each of the five building projects being considered.

Interviews with the teams will be held tomorrow with the committee tentatively scheduled to present its recommendations to the full Horry County Schools Board of Education at its October 12, 2015 workshop for an up or down vote on the recommendations.

If the board votes to approve the list as submitted, final negotiations with the winning offering team for each project will begin.

The proposals submitted are for design-build delivery of each of five planned new school facilities. The overall projected total cost of the five new facilities is $150-200 million.

Horry County Schools Building Projects

The Horry County Schools Selection Committee will have another meeting tomorrow regarding the project to build five new schools.

According to sources familiar with the committee, it will be interviewing the three firms still in the selection process, M.B. Kahn Construction, First Floor Energy Positive and Thompson Turner Construction.

The building plan calls for five energy efficient schools to be built with a completion date of all five by August 2017.

According to sources familiar with the committee, the major goal is to select a construction team that will bring the projects to completion on time and within budget.

One of the three finalist teams, M.B. Kahn, had a construction manager contract with Dorchester School District 2 cancelled last year because of increasing costs.

According to Dorchester School District 2 board records, a contract with M.B. Kahn was finalized in June 2013 for Kahn to serve as construction manager of a district building program that included several elementary schools, a middle school and some other improvements.

By March 2014, the same Dorchester School District 2 board voted to terminate the contract with M.B. Kahn.

Horry County Schools Selection Committee

A Horry County Schools committee is scheduled to recommend next month which design-build team has been chosen to build each of five new schools.

After the recommendations are made by the Horry County Schools Selection Committee, the full Horry County School Board will vote either up or down on the recommendations.

The three teams remaining in the selection process are First Floor Energy Positive, Thompson Turner Construction and M.B. Kahn Construction Co.

Each team submitted two to five specific projects to be evaluated. Evaluation of each proposal will include school district emphasis on the ability to deliver high quality, energy positive schools.

According to sources familiar with the process, the Selection Committee is scheduled to complete its work by October 12, 2015. However, those sources say this deadline may be difficult to achieve.

Of the three remaining teams, M.B. Kahn is the most familiar to Horry County.

It served as the project manager for the new terminal building at Myrtle Beach International Airport.